- The ECG Group
- Valley Stream 30 UFSD
Valley Stream 30 UFSD
Valley Stream, NY

Project Overview
The ECG Group and the Valley Stream 30 Union Free School District began planning the Energy Performance Contract back in the Spring of 2018. Over the course of several meetings with District staff, The ECG Group was able to frame out an Energy Performance Contract opportunity that met the goal of the BOE, generated massive energy savings, and addressed key infrastructure needs.
Through the deployment of LED Lighting Upgrades and Solar PV arrays, the savings from the project were able to fund critical upgrades to the boilers at Clear Stream Avenue School and the elimination of antiquated pneumatic controls district-wide. The District is wrapping up construction in Summer 2020 and they are looking forward to students returning in the fall to an improved and more comfortable learning environment.
Highlights
ECG’s risk-free, no obligation approach gave the District the confidence to move this initiative forward.
The Valley Stream 30 Union Free School District was originally skeptical on whether the opportunity for an EPC existed because they had explored this initiative several times over the years, but they were always told their annual energy spend did not justify a comprehensive project. ECG’s Engineers took a fresh look at the opportunity and identified applications for comprehensive LED lighting and Solar PV. Recent advances in this technology and the enhanced economics helped to drive savings to fund major capital upgrades district-wide and the District is now looking forward to over 80% reduction in utility bills. ECG’s risk-free, no obligation approach gave the District the confidence to move this initiative forward and dig into every last opportunity for energy savings in their buildings.
Five Examples of the 8 Energy Conservation Measures:- LED Lighting
- Solar PV
- Pneumatic-DDC Temp Control Conversions
- Boiler Upgrades
- Oil-Gas Conversion
Project Statistics
PROJECT SIZE$5.2 Million
Projected Energy Savings (Annual)$310,729
Reduction in Energy Costs82%
CompletedEst. Summer 2020
Project TypeEnergy Performance Contract
Energy Service CompanyHoneywell
CLIENT REFERENCE
Dr. Nicholas Stirling, Superintendent of Schools,
Valley Stream District 30
(516) 434-3600
They were very, very thorough. There was never a point where we were confused or could not understand what was actually happening.
Dr. Nicholas StirlingSuperintendent of Valley Stream Union Free School District 30
Related Projects