Pinebush Central SD
Pine Bush, NY

Project Overview
Earlier this month (July 2018), the ECG Group assisted the Pine Bush Central School District in executing an Energy Performance Contract with Ameresco. The ECG Team is currently working to submit the project plans and specifications for submission to the New York State Education Department by the end of July. Components of this project will include: a comprehensive LED upgrade; elimination of pneumatic controls; and installation of over 1.5 MW of roof-mounted Solar PV.
It is estimated that permits and approvals will be in place for construction beginning early summer 2019.
Highlights
Highlights to come
Project Statistics
Project Size$7+ Million
Projected Energy Savings (Annual)$422,000
Reduction in Energy Cost30%
Completed DateProjected for Fall 2020
Project TypeEnergy Performance Contract
Energy Services CompanyAmeresco